Integración
Energética Argentina (IEASA), successor to ENARSA, has published the bidding
documents and specifications for Ensenada de Barragán and Brigadier López
thermal power plants. The sale of these two power plants by the Argentine
Government, for which it expects to raise about US $1 billion, began on
Tuesday, June 12, following the publication of the bidding documents by IEASA.
IEASA will
tender the sale and transfer of the goodwill for both power plants. In
addition, this tender opportunity will include the current contracts (including
the supply agreement with Cammesa, a wholesale electricity market administrator
in Argentina), the debt received for financing the construction of the power
plants, and the obligation to complete the works related to closing the fuel
cycle, which will increase the current capacity of both power plants by 50%.
Hugo
Balboa, head of IEASA, said the bidding documents and specifications for these
thermal power plants were drafted following receiving more than 240 comments
through a pre-qualification questionnaire (PQQ) during a public consultation
period, which attracted the interest of a number of local and foreign
investors.
Companies
that acquire the bidding documents -which in the case of Brigadier López will
cost US $10,000 and US $20,000 in the case of Ensenada de Barragán- will have
90 days to submit their bids. Afterwards, there will be an evaluation period
and the final decision will be announced towards the end of September.
The launch
of the bidding process -currently under the ownership and operation of IEASA
for both power plants in open cycle- will move ahead, although the valuation by
the National Appraisal Tribunal (Tribunal de Tasaciones de la Nación) has not
been completed yet. Nevertheless, according to Mr. Balboa, this information
will be delivered to the interested parties very soon.
Ensenada de
Barragán power plant has an installed capacity of 560 MW, while Brigadier
López, located in the Sauce Viejo industrial park in the Province of Santa Fe,
reaches 280 MW. Companies that are awarded the contract will have the
obligation to complete the works related to closing the fuel cycle, which is
already in advanced execution stage, and will increase the potential installed
capacity of both power plants by 50%, to 840 and 420 MW respectively.
The work to
complete the steam turbine equipments (already completed 90% in both cases)
must be completed within 24 months after the transfer of operation in the case
of Ensenada de Barragán and within14 months in the case of Brigadier López. In
this regard, IEASA notes that all the necessary equipments (generator, turbine,
condenser, etc.) to complete the project are already placed in the plants.
Currently,
some infrastructure works, as well as the supply and assembly of mechanical
equipments, both in the power plants and in the water intakes and aqueduct are
being finalized. In Barragán, the corresponding environmental permit is also
pending.
The tender
opportunities for both Ensenada de Barragán and Brigadier López power plants
present a great investment potential. If you need further assistance regarding
the bidding process, please contact institucionales@berettagodoy.com at Beretta Godoy.
Federico Godoy, Partner
godoy@berettagodoy.comSilvia Kederian
Kederian@berettagodoy.com info@berettagodoy.comContact Us